Further on is a list of upcoming and completed project milestones with more information. The form before it will allow you to filter the timeline to milestones for a single project.

Dartmouth General Hospital

The Dartmouth General Hospital is an integral part of QEll Redevelopment project. The expansion involves adding space for 48 more inpatient beds and doubling the number of operating rooms from 4 to 8. As a result, about 3,500 more surgeries will be performed in Dartmouth every year, and less interrupted care. This is in addition to renovations to the 3rd and 4th floors which is now complete.

All Dartmouth General Hospital Projects

Renovations and Addition

Summer 2012
Renovations and Addition
Planning

Planning activities began in the Summer of 2012 and were completed in the Winter of 2015.

Fall 2015 - Summer 2018
Renovations and Addition
Design

Design activities began in Fall of 2015 and are targeted for completion in Summer of 2018.

Fall 2016
Renovations and Addition
Award of RFP for Construction Management

The province awarded the contract for construction management services for Dartmouth General Hospital's expansion and further renovations to PCL Constructors Canada Inc.

Fall 2016
Renovations and Addition
Dartmouth General Hospital Moves Toward Energy Efficient Addition

New additions to the QEII redevelopment project will be energy efficient by meeting a high energy-efficient standard called a LEED (Leadership in Energy and Environmental Design) rating. This approach will minimize the amount of energy used and energy costs throughout the life of these buildings. We are targeting a LEED gold rating for all new additions in this project. To learn more about LEED, check out this video.

Spring 2017 - Winter 2022
Renovations and Addition
Construction

Construction activities will begin in Spring of 2017 and are targeted for completion in Winter of 2022 and maybe beyond. Construction Outcome: 4 additional ORs, 48 additional beds, updated pharmacy and ICU.